Gigaclear Works, 16 July – 21 Aug

After discussion with Gigaclear and West Berkshire Council, a schedule for the next phase of Gigaclear works has been agreed.

Work will commence on Monday 16th July and the following roads will be affected:
16 – 19 July, Reading Road (from east as far as Police station)
16 – 17 July, Briars Close
16 – 27 July, Mon-Sat – Pangbourne Hill
19 – 27 July, Mon-Sat – Purley Rise
29 July – 2 August, Sunday Only – Reading Road (eastward from police station)
18 – 21 August, Mon-Sat – Horseshoe Road
26 August – 16 September, Sunday Only – Whitchurch Road (before the bridge)

Details will be available on roadworks.org